Every emergency lighting scheme answers one question: when the general supply dies, where does the energy come from for the ninety minutes or three hours that follow?
There are two answers — each fitting carries its own battery, or a shared plant feeds them all — and the choice changes the cable, the upkeep regime and the way a renovation is phased. This guide compares the two on the criteria that actually decide hotel projects.
The topology decision is usually made early and quietly. It appears as a line in a design narrative, or as a column heading in a services schedule, and by the time the lighting package is tendered it is treated as settled.
That is a mistake worth correcting, because the two arrangements are not interchangeable versions of the same thing. They differ in where the battery sits, how much copper runs through the building, who finds a failed unit and when, what happens to a floor during a duration test, and how easily the system grows.
This article sets out how each arrangement works, which project traits push a scheme towards one or the other, the constraints each brings that are easy to overlook at schedule stage. The fields a spec needs in order to make the choice explicit rather than inherited.
It assumes the framing set out in our guide to emergency lighting needs by market — that the safety layer is a separate, code-driven system rather than a feature of the lighting design — and it stays on the building side rather than the product side covered by our emergency lighting product guide.
- 01The choice is about where the energy sits
- 02How each arrangement works
- 03What actually decides it on a hotel project
- 04The central system’s real constraints: distance and segregation
- 05Monitoring: who finds the failed unit, and when
- 06The fleet arithmetic of battery replacement
- 07Phasing, renovation and expansion
- 08A decision framework and the fields to specify
01The Choice Is About Where the Energy Sits
Emergency lighting has to survive the loss of the general supply, which means the energy for it has to be stored somewhere outside that supply. There are only two places it can sit: distributed inside the fittings, or concentrated in one plant. Every practical difference between the two families follows from that single fact.
It is worth separating this decision from three nearby ones that are often confused with it. The first is the operating mode: whether a fitting is lit continuously and takes over on failure, or stays dark until the supply is lost.
That is a per-zone decision and is independent of where the battery sits. The second is the duration need, which is set by the destination market and the building’s evacuation plan and determines how much stored energy is needed, not where it is kept.
The third is monitoring — how the operator learns that a unit has failed — which is a separate layer that can be applied to either arrangement. Keeping these four questions apart prevents a common confusion in which a monitoring decision is mistaken for an building decision.
The reason the building question deserves attention out of proportion to its apparent complexity is that it is one of the few lighting decisions that is genuinely costly to reverse.
Cable routes, distribution board capacity and plant room space are all fixed by the structure of the building. Once the first fix has closed, a project that chose one arrangement can only move to the other by opening the fabric back up.
02How Each Arrangement Works
The two families have a vocabulary of their own, and using it consistently is the fastest way to keep a spec unambiguous.
Self-contained units. Each luminaire contains its own battery, charger and changeover arrangement. Under normal conditions the unit runs from the general supply and its battery is held charged; when the supply fails, the unit transfers to its internal battery and keeps the lamp or the emergency lamp lit for the rated duration.
Nothing outside the fitting decides whether it works, which is the central virtue of the arrangement: a fault affects one unit.
A central system. The battery, the charger and the changeover equipment sit in a plant room, and a dedicated distribution circuit carries the emergency supply out into the building.
The luminaires on that circuit — often called slave or non-self-contained fittings — contain no battery at all; they simply receive power from whichever supply is live. The energy store is a single, supervised asset.
| Site | Self-contained units | Central system |
|---|---|---|
| Where the energy is stored | Inside every fitting on the scheme | In one plant-room battery fitting |
| Effect of a single failure | One fitting loses its emergency function | The whole circuit on that supply loses it |
| Distribution to the fixtures | Standard final circuits | A separate, protected emergency distribution circuit |
| What the fitting contains | Battery, charger, changeover, light source | Light source and control gear only |
| Where battery work happens | At ceiling level, throughout the building | In the plant room |
| Adding a fitting later | Connect it to a circuit and it is complete | Needs spare capacity on the circuit and the plant |
| Testing impact | Per fitting; a duration test can be staged by area | A test discharges the shared battery, so the circuit’s coverage is affected together |
| Commissioning effort | Distributed across the whole fitting | Concentrated at the plant plus circuit verification |
That table already explains most real-world preferences. A small site with a few dozen fittings, a phased refurbishment or an awkward existing building tends to suit distributed storage because nothing has to be routed specially and nothing depends on a plant room being found.
A large site with a services infrastructure, a upkeep team and a need for one supervised energy store tends to suit a central system, gave the distribution can be designed properly at first fix.
03What Actually Decides It on a Hotel Project
In practice, five traits of the project carry most of the decision. Working through them in order is faster than starting from a preference.
- Scale and distribution of the emergency load. A scheme whose fittings are spread thinly across a large campus makes a central distribution circuit long and hard to protect; a scheme concentrated in circulation cores makes it short and manageable. Distributed storage is indifferent to distance because each unit is fed from a local circuit.
- Whether a plant room exists and can be protected. A central battery fitting needs a dedicated, ventilated, accessible and fire-protected space, with room for the battery bank, the charger and the distribution equipment. If the building has no such space, the central option is not a matter of cost but of feasibility.
- The operator’s upkeep capability. A central system concentrates the routine work where a facilities team already goes. Distributed storage scatters it across ceilings. That is an strength where the team is small and a disadvantage where a single point of failure is dangerous.
- Whether the project is a new build or an intervention in a working building. Distributed storage is far easier to add to an existing fitting and far easier to stage floor by floor. An existing building whose first fix cannot be reopened well rules out a central distribution circuit.
- How the building will be used in ten years. A central system with spare capacity can absorb a change of use more easily than one sized exactly to the original scheme, but it only has that range if the headroom was specified at the outset.
Two further factors sit alongside those. The first is style: self-contained units are generally bulkier, because a battery compartment has to live inside the housing, which matters where the fitting is visible in a corridor or a lobby — our notes on corridor lighting design cover the constraints of that setting.
Central-system slave fittings have no battery compartment and are correspondingly slimmer. The second is the interaction with decor fittings: a chandelier is never an emergency luminaire, and neither arrangement changes that. The building is the safety layer, and the decor scheme sits beside it, as explained in our analysis of control systems and the safety layer.
04The Central System’s Real Constraints: Distance and Segregation
Central systems are often chosen for reasons of upkeep economy, and then designed as though they were ordinary power circuits. Two constraints decide whether a central scheme behaves well.
Distribution voltage and voltage drop. Where a central fitting distributes at a low voltage, the current for a given load is higher, and volt drop along the cable turns a design constraint rather than a detail.
A long run to a distant wing can leave the furthest fitting with less than the intended supply, which affects the emergency output and, in the worst case, whether the unit operates at all. The remedy is design: keep runs short, increase conductor size, or distribute at a higher voltage.
The point for a spec is that the plant’s location is a lighting decision as much as a services decision, and the furthest fitting on each circuit should be checked rather than assumed.
Segregation and protection of the emergency circuit. The emergency distribution must be separate from the general lighting circuits and arranged so that a fault, an isolating switch or a upkeep operation on the normal lighting cannot take the safety layer with it.
In practice this means a dedicated circuit path, protection appropriate to the arrangement, and a cable route that survives the conditions in which it will be needed. Where the route has to pass through areas of fire risk, the route itself turns part of the safety design.
These are services-engineering decisions, but they are decided in the same coordination meetings as the lighting layout, and a lighting package that assumes they will be resolved later creates a delay.
One practical consequence of a shared supply deserves a place in the commissioning record: because the emergency circuit is fed from the plant, a works operation at the plant can affect a whole zone’s emergency coverage.
The handover should so state clearly which work need the plant to be isolated, and what provision covers the affected area while that work is being done. Our guide to commissioning and handover treats procedures of this kind as deliverables rather than as notes.

05Monitoring: Who Finds the Failed Unit, and When
Emergency lighting is unusual among building systems in that its failures are invisible most of the time. A fitting with a dead battery looks exactly like a fitting with a healthy one until the supply fails or until someone tests it. The arrangement you choose determines how quickly a failure is discovered, and by whom.
With distributed storage, the discovery mechanism is either a manual inspection round or a monitoring layer. The manual version is a scheduled walk-through in which each unit is examined, and it consumes time in proportion to the number of fittings — a hotel with several hundred units is not a small round.
The monitored version uses self-testing circuitry inside each unit, which exercises the fitting on a schedule and reports the result, so that the routine turns an exception report rather than an inspection.
The power of that layer depends on the communication path back to the operator: a self-test function that reports to a panel nobody reads has not solved the problem.
With a central system the supervision model is different in kind. The battery fitting is one asset, and its condition can be monitored directly — charge state, mains presence, and the health of the changeover arrangement. That is a genuine strength, because the most stressed part in the whole scheme sits in one place and can be instrumented properly.
The limitation is that the plant’s health says nothing about whether an individual slave fitting is producing light. Circuit integrity and luminaire function are separate questions, and a well made central scheme still needs a means of confirming that each fitting on the circuit actually illuminates.
The practical implication is that the monitoring layer should be specified as a need in its own right, whatever the topology:
| Question the operator needs answered | Self-contained units | Central system |
|---|---|---|
| Is the stored energy healthy? | Per-fitting self-test, or a manual round | Directly, at the plant |
| Did the fitting illuminate on test? | Per-fitting self-test, or a manual round | Needs per-fitting monitoring or circuit-level checks |
| Where is the fault? | Reported per fitting | Reported for the circuit, and then located by inspection |
| How much of the scheme is affected by one fault? | One fitting | One circuit |
| What does the routine cost in labour? | High without monitoring; low with it | Low at the plant; plus periodic fitting verification |
Whichever route is taken, the records belong to the operator and should be designed for from the start. The need to show that the scheme is tested and functioning does not disappear because monitoring exists; it changes form, from a signed round sheet to an exported report.
That is why the handover should state, in writing, how test results are retrieved, how long they are retained and who is responsible for reading them. Our notes on pre-shipment inspection describe the same rule applied to the equipment before it leaves the plant: evidence that is not captured at the right moment cannot be reconstructed afterwards.
06The Fleet Arithmetic of Battery Replacement
Batteries are consumables, and the difference between the two arrangements is not whether they will be replaced but how many times, and where.
With distributed storage, the operator eventually faces a large number of small replacements distributed through the building. The work is low-skill and repetitive but awkward: access to a ceiling, protection of the finishes, and the risk that a replacement is done with an unsuitable cell.
The mitigating measures are a serviceable fitting — a battery that can be changed without dismantling the luminaire — and a spares position that keeps the correct cell type in stock. Both are spec decisions. Our checklist for designing fixtures for upkeep covers the access, spares and documentation questions in detail.
With a central system there is one replacement event, performed in a controlled space by a competent party, with a single spec for the cells.
Against that, a central bank is a large investment, and its replacement may need a planned interruption of the emergency supply to part or all of the building — which means temporary cover has to be arranged while the work proceeds. It also means the scheme has one concentrated date on which a marked upkeep cost falls due, rather than a gradual accumulation of small ones.
Two engineering points affect the arithmetic on both sides. The first is temperature. Battery capacity and service life depend strongly on the temperature they live in, and the two arrangements place them in very different spaces: a plant room can be kept at a controlled temperature, while the space above a hotel corridor ceiling is routinely warmer than the room below it, mostly on upper floors and under roofs.
A distributed scheme in a hot ceiling void will consume batteries faster than the same scheme in a temperate one, so the expected replacement interval should be stated for the space, not in the abstract.
The second is sizing. A central bank is usually sized for the load at the end of its design life rather than at the start, because capacity falls as the battery ages and the required duration has to be met on the day of the test, not on the day of fitting.
The margin that results is a legitimate part of the design, and it should appear in the spec rather than being absorbed invisibly.
07Phasing, Renovation and Expansion
Hotel projects rarely arrive complete. Floors are handed over in sequence, wings are refurbished in rotation, and a scheme commissioned in one year is extended in another. How gracefully a topology absorbs that is one of the more underrated selection criteria.
Distributed storage is intrinsically modular. A new floor is a new set of circuits; each fitting brings its own energy store, and the existing fitting is untouched.
A refurbishment of one wing can proceed while the rest of the building operates, and a fitting added later is functionally complete as soon as it is connected and tested. Where a project is being gave in phases, or where the building must remain occupied throughout, this site alone often settles the decision.
A central system is modular only up to the capacity that was designed in. Adding a floor means adding load to a circuit and a battery sized for the original scheme, and if the headroom was not specified at the outset the extension turns a project in its own right — a new plant, a supplementary circuit, or a partial migration to self-contained units.
That is not a reason to avoid a central system; it is a reason to size it for an agreed future condition and to record that assumption.
The failure mode is a plant sized precisely to the opening scheme, with the extensions left undiscussed because they belong to a later phase. Where a building is being refurbished rather than extended, our notes on mechanical and ceiling checks in renovation lighting set out the surveys that should precede a decision to reuse existing routes.

08A Decision Framework and the Fields to Specify
The five traits in section 03 can be cut to a short screening sequence, which is useful where a scheme has to be settled in a coordination meeting rather than by study.
- Is there a protected, ventilated plant space with room for a bank and its access needs? If not, the central option is closed and the rest of the sequence does not apply.
- Can a dedicated emergency distribution route be designed at first fix without crossing protected or inaccessible zones? If not, distributed storage is the realistic answer.
- Is the emergency load concentrated in cores and circulation, or spread thinly across a wide plan? Concentrated load favours a central plant; a wide dispersion favours distributed storage.
- Will the building be extended, re-planned or refurbished in phases over the next decade? Heavy phasing favours distributed storage.
- Does the operator prefer one supervised asset and a controlled upkeep space, and can they meet the concentration risk with monitoring? If yes, a central system can be the better long-term arrangement.
Whichever way that resolves, the spec should record the choice explicitly rather than allowing it to be inherited. The fields that make the arrangement unambiguous are set out below.
| Field | What to state |
|---|---|
| Topology | Distributed, central, or a mixed arrangement, named zone by zone rather than as a project note |
| Operating mode | Kept, non-kept or mixed, by zone |
| Duration | The required emergency duration for the building, with the battery sized to meet it at end of life |
| Energy store | Chemistry, expected service life at the ambient temperature of its location, and whether it is field-replaceable |
| Distribution | Where the plant sits, the distribution voltage, the furthest fitting on each circuit, and the segregation and protection arrangements |
| Monitoring | What is monitored, at what granularity, where results are reported, and who reads them |
| Testing provision | How a functional test and a duration test are performed, and what temporary cover a plant test needs |
| Expansion | The future load the plant and circuits are sized for, recorded as an assumption |
| Handover | Circuit and zone schedules, test records, isolation procedures, spares position and the evidence pack for the equipment supplied |
Two closing notes on scope. First, the applicable needs for emergency lighting — what has to be lit, for how long, and to what standard of evidence — are fixed by the destination market and confirmed by the project’s own electrical engineer and the authority that inspects the fitting.
The comparison above is about building, not about compliance. Second, the equipment itself still has to be evidenced: a topology decision does not show that the fittings supplied are suitable for the role.
Our guide to certification and listing evidence explains how that chain of documents works, and our notes on briefing a lighting maker set out how to ask for it in the enquiry rather than after the order.
Source type: the building descriptions, monitoring behaviour and upkeep consequences above reflect published emergency-lighting standards and national codes, guidance issued by testing and certification bodies, and general trade practice among lighting suppliers serving hospitality projects. Illuminance levels, durations, monitoring needs, testing intervals and acceptance criteria vary by market and by building, and the applicable edition and any local amendments govern; confirm them with the project’s electrical engineer and the authority having jurisdiction. Where a figure is quoted in this article it is indicative practice, not a design value.
Frequently Asked Questions
Which arrangement is better for a hotel?
Neither is better in the abstract. Distributed storage suits phased work, awkward existing buildings, wide plans and smaller sites, because nothing has to be routed specially and a fault affects one fitting.
A central plant suits large sites with concentrated circulation, an existing services infrastructure and a facilities team that prefers one supervised asset. The screening sequence in section 08 is a faster route to an answer than a preference.
Does a central system remove the need to test individual fittings?
No. Supervising the plant tells you about the battery, the charger and the changeover equipment; it does not tell you whether a particular slave fitting produces light when the supply fails.
Circuit integrity and luminaire function are separate questions, so a central scheme still needs a means of confirming each fitting. This is one of the most commonly overlooked needs when a central system is chosen for its upkeep economy.
Why does voltage drop matter more on central systems?
Because the energy is gave from one point rather than stored locally, so the cable run is part of the design. Where distribution is at a low voltage, the current for a given load is higher and the permissible run is shorter; a distant wing can end up at the far end of a long cable with less supply than intended.
The remedies are design remedies — shorter runs, larger conductors or a higher distribution voltage — and the check belongs in the design rather than in commissioning.
How long do the batteries last?
It depends on the chemistry, the depth and frequency of discharge and, strongly, on the temperature of the space the battery lives in.
That is why the expected service life should be stated for the actual location — a plant room and a ceiling void are different spaces — rather than quoted as a single figure for the product family. Replacement is a planned upkeep activity in both arrangements, not an exceptional event.
Can a building use both arrangements?
Yes, and mixed schemes are common in practice: distributed storage in an existing wing added to a central system serving a new core, or self-contained units in an area where the emergency circuit cannot reach.
Where this happens, the spec should describe the arrangement zone by zone and make the boundary explicit, so that the two parts are separately testable and separately documented.
What temporary cover is needed while the plant is serviced?
Any operation that isolates the emergency supply cuts coverage for the circuit it feeds, so the affected area needs either a temporary arrangement or an agreed period in which the building is not occupied.
The workable approach is to plan the operation, record it and confirm the provision in advance; the need should be identified at handover rather than discovered when the first service visit is booked.
Does the choice affect the decor lighting package?
It affects the fittings that sit in visible positions. A self-contained unit has to house a battery compartment, so it is generally bulkier than a slave fitting with no battery, and that difference shows in a corridor or a lobby.
It does not change the rule that a decor luminaire is never an emergency luminaire: the safety layer stands beside the decor scheme, not inside it.
Choosing an Emergency Lighting Building?
Send us the floor plans with the emergency fittings marked, the location and size of any plant space, the phasing plan and the duration the building has to meet.
We will tell you where a central distribution route will cause difficulty, which circuits will carry the most fittings, and what monitoring the scheme needs so that a failed unit is found before an inspection finds it for you.
Three companion pieces sit alongside this one. Our guide to emergency lighting needs by market covers what has to be lit and for how long, our product guide covers the fittings, signs and batteries themselves, and our article on smart controls and the safety layer explains where the control system stops and the safety system starts.
Where the scheme has to be added to a building in use, our notes on renovation lighting checks cover the surveys that come first, and where the emergency circuits feed visible circulation spaces, our guide to corridor lighting design covers the coordination that keeps the two layers readable. Talk to our team